This project will replace all of the HVAC and plumbing systems in Gray Hall. Chilled water will be extended to Gray from the existing Central Campus Chiller plant and a fire sprinkler system will be added at the request of our insurance carrier
Budget = $9,052,773
Schedule - Design Phase = Summer/Fall 2024 - Winter 2025 Construction = Summer 2025 - Summer 2026