Jump to main content

Gray Hall Mechanical

This project will replace all of the HVAC and plumbing systems in Gray Hall. Chilled water will be extended to Gray from the existing Central Campus Chiller plant and a fire sprinkler system will be added at the request of our insurance carrier

Budget = $9,052,773

Schedule - Design Phase = Summer/Fall 2024 - Winter 2025          Construction = Summer 2025 - Summer 2026