Arts Annex Sprinklers
This project will add fire sprinklers to the Arts Annex addition
Budget = $242,722
Construction Schedule – Spring 2024
Art Annex Sprinklers: Sprinkler piping completed, fire alarm hardware to be installed spring break ’24, project delayed for lead times on electrical fire alarm equipment. Total project due to be completed by end of March ’24 at or near original budget $242,722.